Perfect punch-out on challenging motor job in France

In October 2026, Brownline surveyed a challenging mud motor HDD crossing in northeastern France. For the construction of a new high-voltage connection, a river was crossed, and drilling had to be carried out through very hard layers.

Background of the project

For the expansion of the electricity network, a new 63 kV connection is being built between high-voltage stations in Biberkirch and Cirey-sur-Vezouze. The route is laid underground to minimize disruption to the environment. At Cirey-sur-Vezouze, the route crosses the river Vezouze. To cross the river without disturbance, a 310 m / 1017 ft directional drill was made here.

Our client Infra Group carried out the drilling operations. To ensure the highest accuracy, they relied on Brownline to survey the pilot bore.

Extremely hard soil

The crossing was drilled with a mud motor because the soil was extremely hard. It consisted of hardened layers of marl and sandstone. Absolute precision in the pilot phase was required to safely cross the river under these challenging conditions. To that end, the Drillguide Gyro Steering Tool was used behind the mud motor to survey the pilot.

Thanks to the real-time measurements of the Drillguide GST, it was possible to continuously monitor the drilling process. Deviations caused by the difficult subsoil can be instantly recognized with these real-time measurements, allowing for steering adjustments before the deviation becomes too large.

Perfect punch-out

Before the drill crossed a forest, a measurement with GPS track was carried out in a meadow. This independent verification from the surface confirmed the gyro measurements, allowing for extra confidence when drilling under the forest and river. During drilling, the mud pressure was also closely monitored using Brownline’s Pressure-While-Drilling service. This monitoring greatly reduced the risk of inadvertent mud returns under the forest and river.

Thanks to the precise steering service, the drill punched out perfectly at the exit stake, as can be seen here in the accompanying video. A result that all parties can be very satisfied with.

"Thank you for the smooth collaboration."
Team D100
2tone Brownline Drillguide Verbraeken Infra Group Cirey-sur-Vezouze HDD river crossing
Photo  5
Photo  14
Photo  2
Specifications
Length
310 m / 1017 ft
Depth
18 m / 59 ft
Entry angle
-18°
Exit angle
16°
Radius
210 m / 689 ft
PWD
✓
Assembly
Mud motor
Product pipe
HDPE bundle